https://www.whatdotheyknow.com/request/the_drove_stonehenge#incoming-3163421 explains the repair planning process:
"Please note there is no formal plan - works have been undertaken on a “Walk, Talk, Build” Basis. The Walk, Talk, Build process is a collaborative and phased approach often used in construction and infrastructure projects to ensure stakeholder engagement, clarity of scope, and smooth delivery. I am satisfied you have otherwise received all the reports we hold in relation to the ‘scope of works’ as requested."
"The response in relation to asbestos was a verbal report of the presence of asbestos received from English Heritage Staff on the site. The initial indications being that this material originates from the 1st world war airfield hangers that were on the site. Whilst a verbal report was received, there has never been the necessity to have a technical report compiled on the asbestos."
No comments:
Post a Comment
Comments welcome on fresh posts - you just need a Google account to do so.